With only two functioning power plants out of the 24 power plants in Nigeria, power generation is said to have dipped to 916MW as at 14:00 hours on Sunday.
Notably, the decline in the power generation was from 3,787.60MW produced by 17 power plants at 13:00 hours of the same day.
The two power plants in operation were Egbin (Steam), which generated 680 MW with four units and Geregu (Gas) which produced 236 MW with two units.
This was contained in the document of the Independent System Operator (SO) titled: “List of GenCos and their MW Load @ 14:00 hrs on 15/01/2023.”
The plants that generated 3,787.60MW, according to another document titled: “List of GenCos and their MW Load @ 13 hrs on 15/01/2023,” were Afam VI (Steam) 14OMW, Alaoji NIPP (Gas) 103.10MW, Azura-Edo IPP (Gas) 420MW and Dandikowa GS (Hydro) 32.30MW.